Marsh Road, Gurnard, Isle Of Wight
31 July — 24 September Road closure
Delays likely due to Streetworks
Carriageway Reconstruction, Planing And Resurfacing. (Ff-Stren110:R/H3, Strengthen 25mm Ul-M 65psv And 85mm Foambase-Rural:H3) Gurnar at Gurnard: From Rew Street To Lower Church Road (Ml130069) : Marsh Road-Gurnard:; Stacey Terrett
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

A3055 Blackgang Road, Niton, Isle Of Wight
31 July — 13 August Traffic control (multi-way signals)
Delays possible due to Streetworks
Build 1 Concrete Chamber 915mm X 445mm X 965mm Deep In Footway,Install 60m Of 1 Way Poly Duct In Verge,Install 8m Of 1 Way Poly Duct In Carriageway at 55m West Of Jnc Blackgang Old Road, Jnc Blackgang Old Road On, Blackgang Road.
Responsibility: BT
EToN status: Advanced planning

Blackgang Old Road, Chale, Isle Of Wight
31 July — 13 August Traffic control (multi-way signals)
Delays possible due to Streetworks
Build 1 Concrete Chamber 915mm X 445mm X 965mm Deep In Footway,Install 10m Of 1 Way Poly Duct In Carriageway,Install 5m Of 1 Way Poly Duct In Footway,Install 60m Of 1 Way Poly Duct In Verge at Jnc Blackgang Road, Jnc Chale Footpath 12, And Opp To O/S Ashore Cafe, Blackgang Old Road
Responsibility: BT
EToN status: Advanced planning

Brading Down Road, Brading, Isle Of Wight
31 July — 31 July Traffic control (Stop/Go boards)
Delays possible due to Streetworks
Gully Cleansing Required Under Traffic Management Brading at Brading: On Sharp Bend, Jct Mersley Down Road: Brading Down Road-Brading – 1751
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Chale Footpath 12, Chale, Isle Of Wight
31 July — 13 August Traffic control (multi-way signals)
Delays possible due to Streetworks
Build 1 Concrete Chamber 915mm X 445mm X 965mm Deep In Footway,Install 40m Of 1 Way Poly Duct In Verge at Jnc Blackgang Old Road To 40m South Of Jnc Blackgang Old Road On, Chale Footpath 12.
Responsibility: BT
EToN status: Advanced planning

A3056 Hale Common, Arreton, Isle Of Wight
31 July — 13 August No carriageway incursion
Delays unlikely due to Streetworks
312077 Shanklin 18 – Street Cabinet & Power Installation. Excavate To Lay Approx 12m Bt Ducts, Lay Concrete Plinth, Stand Cab. Excavate To Expose Low Voltage Cable For Power Connection And Lay Approx 55m Duct. Power Engineer To Carry Out Inspection Prior To Jointing. Power Jointing Team To Insert Cable And Execute Jointing Works. Reinstate, Check And Clear Site. at Nr Jctn Of Hale Common & Arreton Bridleway
Responsibility: BT
EToN status: Advanced planning

B3327 High Street, Wroxall, Isle Of Wight
31 July — 07 August Some carriageway incursion
Delays unlikely due to Streetworks
Gsmr/Hse Cut Off 43743 at Os London House
Responsibility: SGN
EToN status: Advanced planning

Station Avenue, Sandown, Isle Of Wight
31 July — 10 August Some carriageway incursion
Delays unlikely due to Streetworks
Relay Service From Nearside Footway To Site at Os 20
Responsibility: SGN
EToN status: Advanced planning

Pelham Close, Bembridge, Isle Of Wight
31 July — 03 August Traffic control (give & take)
Delays unlikely due to Streetworks
Footway Re Construction And Surfacing (Fwl: Bit Partrecon Fwr: Bit Fullrecon ) Bembridge at Bembridge: From Healthfield Road 50m North (Ml 360654): Pelham Close-Bembridge
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Pelham Close, Bembridge, Isle Of Wight
31 July — 03 August Traffic control (give & take)
Delays unlikely due to Streetworks
Footway Re Construction And Surfacing (Fwl: Bit Partrecon Fwr: Bit Partrecon ) Bembridge at Bembridge: From Healthfield Road 50m South (Ml 360653): Pelham Close-Bembridge
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Quarry Road, Ryde, Isle Of Wight
31 July — 03 August Traffic control (give & take)
Delays unlikely due to Streetworks
Footway Re Construction And Surfacing ( Fwr: Bit Partrecon) Ryde at Ryde: From Well Street To Alfred Street (Ml 340441): Quarry Road-Ryde
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Quarry Road, Ryde, Isle Of Wight
31 July — 03 August Traffic control (give & take)
Delays unlikely due to Streetworks
Footway Re Construction And Surfacing (Fwl: Bit Slurry Fwr: Bit Partrecon) Ryde at Ryde: From Well Street To St Johns Hill (Ml 340440): Quarry Road-Ryde
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Sandcroft Avenue, Ryde, Isle Of Wight
31 July — 04 August Traffic control (give & take)
Delays unlikely due to Streetworks
Footway Re Construction And Surfacing ( Fwl: Bit Partrecon Fwr: Bit Partrecon) Ryde at Ryde: Main Spine Of Road From Quarry Road (Ml 340610): Sandcroft Avenue-Ryde
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Sandcroft Avenue, Ryde, Isle Of Wight
31 July — 04 August Traffic control (give & take)
Delays unlikely due to Streetworks
Footway Re Construction And Surfacing ( Fwl: Bit Partrecon Fwr: Bit Partrecon) Ryde at Ryde: Main Spine Of Road From Quarry Road (Ml 340610): Sandcroft Avenue-Ryde
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Well Street, Ryde, Isle Of Wight
31 July — 03 August Traffic control (give & take)
Delays unlikely due to Streetworks
Footway Re Construction And Surfacing (Fwl: Bit Partrecon Fwr: Bit Partrecon ) Ryde at Ryde: From High Street To Prince Street (Ml 340514): Well Street-Ryde
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Well Street, Ryde, Isle Of Wight
31 July — 03 August Traffic control (give & take)
Delays unlikely due to Streetworks
Footway Re Construction And Surfacing (Fwl: Bit Partrecon Fwr: Bit Slurry ) Ryde at Ryde: From Quarry Road To Prince Street (Ml 340515): Well Street-Ryde
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Wellington Road, Newport, Isle Of Wight
31 July — 04 August Traffic control (give & take)
Delays unlikely due to Streetworks
Footway Reconstruction And Surfacing (Fwl: Bit Partrecon Fwr: Bit Partrecon) Newport at Newport: From Carisbrooke Road 250m North (Ml 230232): Wellington Road-Newport
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Wellington Road, Newport, Isle Of Wight
31 July — 04 August Traffic control (give & take)
Delays unlikely due to Streetworks
Footway Reconstruction And Surfacing (Fwl: Bit Partrecon Fwr: Bit Partrecon) Newport at Newport: From Mountbatten Drive 250m South (Ml230233): Wellington Road-Newport
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Wilkes Road, Sandown, Isle Of Wight
31 July — 06 August Some carriageway incursion
Delays unlikely due to Streetworks
Scaffold (Lowes Scaffold) at O/S 3
Responsibility: Island Roads on behalf of the Isle of Wight Council