Check our weekly list of roadworks and road closures for more precise details of when works will start in your area.
Isle of Wight roadworks or road closures starting today or tomorrow. Information provided by Elgin via Roadworks.org
A3020 Blackwater Road, Newport, Isle Of Wight
16 December — 18 December Traffic control (Stop/Go boards)
Delays likely due to Streetworks
Install N? 2 Lanterns (N? 2 Columns) Newport at Newport: At The Junction Of Shide Road & Blackwater Road (Ml 410022):
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning
A3020 St Georges Way, Newport, Isle Of Wight
16 December — 18 December Traffic control (Stop/Go boards)
Delays likely due to Streetworks
Install No 23 Lanterns (No 22 Columns) 3 X 40mph Signs, 3 Warning Signs, 1 Public Notice And 1 Lit Vehicle Activation Sign Newpor at Newport: From Column 27, South To Junction Of Shide Road (Ml 210001, Ml 210002, Ml 210003 And Ml 210004): :; Sl Cip Sche
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning
A3054 Binstead Hill, Binstead, Isle Of Wight
17 December — 19 December Traffic control (multi-way signals)
Delays likely due to Streetworks
P/H That Keeps Breaking Out – Requires A Patch .50 X .35 X 30mm Patch 2.2 X 1.3 X 50/100mm Tm – Suggested Four Way Temp Lights (Cw: Pothole) H1 Urban Binstead at Binstead: On Binstead Hill On Wootton Bound Side Of The C/Way Just Before The Mini Roundabout: Binstead Hill-Binstead
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning
Roseway, Lake, Isle Of Wight
16 December — 18 December Road closure
Delays likely due to Streetworks
– Replace Cover And Frame In Carriageway at 26 Roseway Lake
Responsibility: Southern Water
EToN status: Advanced planning
A3020/A3054 Parkhurst Road, Newport, Isle Of Wight
16 December — 22 December Some carriageway incursion
Delays possible due to Streetworks
– Install Fire Hydrant In Layby. at 2 Horsebridge Hill, Newport, Isle Of Wight.
Responsibility: Southern Water
EToN status: Advanced planning
A3020 Shanklin Road, Godshill, Isle Of Wight
17 December — 19 December Traffic control (two-way signals)
Delays possible due to Streetworks
C/W Ridege And Depression (Suspected Wheelpush). Lengthways Along C/W. Measures 4.25 Metres X 0.5 Metres On West Bound C/W Near Centre Line. Up To 60 Mm Above General Road Surface Needs Saw Cut. Tm Best Done At Night. 2way Lights. (Cw: Pothole) H1 Urban Godshill at Godshill: On The “S” Bend After The Gulf Petrol Station. Opp Barrow Cottage.: Shanklin Road-Godshill
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning
A3055 East Hill Road, Ryde, Isle Of Wight
17 December — 19 December Traffic control (multi-way signals)
Delays possible due to Streetworks
Sawcut And Infill P/H’S X 2 One On Nearside Tyreline And The Other On The Offside Tyreline ,45 X .35 X 50mm .60 X .60 X 40mm Tm – Suggested Four Way Temp Lights (Cw: Pothole) H1 Urban Ryde at Ryde: On The Sandown Bound Side Of The C/Way O/S Rougemont Flats, Easthill Road, Ryde: East Hill Road-Ryde
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning
A3055 Esplanade, Ryde, Isle Of Wight
17 December — 19 December Lane closure
Delays possible due to Streetworks
Idr – Ironwork Cover Breaking Out Requires Resetting 1.80 X 1.20 X 50/100mm Tm – Lane Closure Ryde at Ryde: On The Roundabout At The End Of The Esplanade On The Inside Sandown Bound Lane: Esplanade-Ryde
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning
B3399/B3401 Freshwater Road, Shalfleet, Isle Of Wight
17 December — 17 December Traffic control (two-way signals)
Delays possible due to Streetworks
Access Required To Underground Bt Structure To Provide Service – No Structural Changes. Work Being Carried Out On Existing Bt Plant at Freshwater Road Near The Junction Of Dodpits Lane And Brook Road Shalfleet Po41 0ud
Responsibility: BT
EToN status: Advanced planning
B3399 Brighstone Road, Brook, Isle Of Wight
16 December — 17 December Traffic control (two-way signals)
Delays possible due to Streetworks
313495 Brook – Fpc – Fibre Path Clearance – Interim To Permanent Reinstatement at In C/W Approx 45m West Of Jnc Church Lane O/S Church Of St Peter & St Paul Mottistone
Responsibility: BT
EToN status: Advanced planning
B3399 Brook Road, Brighstone, Isle Of Wight
16 December — 17 December Traffic control (two-way signals)
Delays possible due to Streetworks
Brightstone – 315409 Seg Ref: Smjbri444 – Interim To Permanent Reinstatement at Approx 43m West Entrance Petite Place, Brook Road, Brighstone, Iow
Responsibility: BT
EToN status: Advanced planning
B3399 Limerstone Road, Brighstone, Isle Of Wight
16 December — 17 December Traffic control (two-way signals)
Delays possible due to Streetworks
Brightstone – 313495 – Bduk – Fpc – Fibre Path Clearance – Interim To Permanent Reinstatement at 74m E Limerstone Cottage
Responsibility: BT
EToN status: Advanced planning
B3399 Main Road, Brighstone, Isle Of Wight
16 December — 17 December Traffic control (two-way signals)
Delays possible due to Streetworks
Shanklin – 317888 Jg030 Fpc – Interim To Permanent Works In Carriageway at In C/W O/S Shelley & Brierley, Main Road
Responsibility: BT
EToN status: Advanced planning
B3399 Main Road, Brighstone, Isle Of Wight
16 December — 17 December Traffic control (two-way signals)
Delays possible due to Streetworks
Shanklin – 317888 Jg029 Interim To Permanent Works In Carriageway at In C/W Os Pastures, Chiltern Lane, On Main Road, Brighstone
Responsibility: BT
EToN status: Advanced planning
B3401 Shide Road, Newport, Isle Of Wight
16 December — 18 December Traffic control (Stop/Go boards)
Delays possible due to Streetworks
Install No 17 Lanterns (No 17 Columns) Newpor at Newport: From Blackwater Road, West To Whitepit Lane (Ml 230106, 230105 And Ml 230104): :; Sl Cip Scheme Sl Cip Scheme
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning
Esplanade, Sandown, Isle Of Wight
16 December — 18 December Traffic control (Stop/Go boards)
Delays possible due to Streetworks
Install N? 44 Lanterns (N? 24 Columns) 1 No Waiting Sign, 2 Route/Direction Signs, 2 Parking Restriction Signs, 8 Resident Parking Permit Signs, 4 Warning Signs, 1 Lit Warning Sign & 22 Festive Decorations Sandown at Sandown: From Revetment, North East To Avenue Slip (Ml 440198, Ml 440199, Ml 440459 & Ml 441200):
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning
Sandy Lane, Shanklin, Isle Of Wight
17 December — 19 December Traffic control (multi-way signals)
Delays possible due to Streetworks
Idr – Ironwork Breaking Out Leaving A 30mm Exposed Edge Reset Gully Cover Tm – Suggested Three Way Temp Lights (Cw: Irnwk Not Exceed +Or- 20mm) Shanklin at Shanklin: Jnc Of Cedar Drive And Whitecross Lane: Sandy Lane-Shanklin
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning
St James Square, Newport, Isle Of Wight
16 December — 18 December Traffic control (Stop/Go boards)
Delays possible due to Streetworks
Install N? 7 Lanterns (N? 1 Column) Newport at Newport: From Junction Of High Street, South To Junction Of Pyle Street (Ml 220078):
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning
Albion Road, Sandown, Isle Of Wight
16 December — 24 December Some carriageway incursion
Delays unlikely due to Streetworks
Lay New Main From Nearside Carriageway To Site at Adj 97 – 101 High Street
Responsibility: SGN
EToN status: Advanced planning
B3325 High Street, Cowes, Isle Of Wight
16 December — 18 December Traffic control (give & take)
Delays unlikely due to Streetworks
Lift The Manhole Cover To The Combined Sewer Overflow To Install Monitoring Equipment. No Excavation at Adj To 73 High Street
Responsibility: Southern Water
EToN status: Advanced planning
B3325 High Street, Cowes, Isle Of Wight
16 December — 31 December Some carriageway incursion
Delays unlikely due to Streetworks
Excavation Of Footway And Carriageway To Install New Electrical Supplies To New Flats At Site Of Waterside Public House. This Is A One Way Road, Traffic Management Not Required – We Will Maintain Min Clearances For Types Of Vehicles Using This Road. at O/S 71 To 74
Responsibility: Southern Electric
EToN status: Advanced planning
Niton Road, Godshill, Isle Of Wight
16 December — 17 December Some carriageway incursion
Delays unlikely due to Streetworks
Chale Green 324495 Overlay – Lay Approx 15m Of Duct 54 In Verge To Link Existing Bt Boxes To Facilitate Spine Cabling Works. at So Leechmore Farm, Niton Road, Junc Of Beacon Alley, Godshill
Responsibility: BT
EToN status: Advanced planning
Car Park Quay Road, Ryde, Isle Of Wight
16 December — 31 December Some carriageway incursion
Delays unlikely due to Streetworks
Scaffold (Island Scaffold) at O/S Ice Rink
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning
Gregory Close, Nettlestone, Isle Of Wight
16 December — 18 December No carriageway incursion
Delays unlikely due to Streetworks
Install 2m Of 1 Way Poly Duct In Footway at O/S 6 , Gregory Close
Responsibility: BT
EToN status: Advanced planning
Monks Brook, Newport, Isle Of Wight
17 December — 21 December Some carriageway incursion
Delays unlikely due to Streetworks
Install 1m Of 1 Way Poly Duct In Footway at 83m North East From Junc Dodnor Lane, Monks Brook
Responsibility: BT
EToN status: Advanced planning
Rew Lane, Wroxall, Isle Of Wight
17 December — 18 December Traffic control (give & take)
Delays unlikely due to Streetworks
Installation Of Asphalt Hump To Prevent Flooding Wroxall at Wroxall: Ml 540226, Outside Span Farm: Rew Lane-Wroxall
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning