Steps along the Bonchurch seafront on 8 Nov 2026

Storms and hard ground delay Ventnor seafront investigations

Environment Agency closes Ventnor office as storms and hard ground delay work

Harder ground than expected beneath the seafront in Ventnor, plus recent storms, has put the Environment Agency’s ground investigations for the Ventnor Coastal Defence Scheme behind schedule.

The agency now expects to finish the last of the investigations by the week ending 10th December, and to clear its site compound off the seafront by the end of the week commencing 14th December 2026.

It has also closed its public project office in the town.

Harder ground than expected
The Environment Agency says the investigations have been “progressing well overall” and are giving its engineers a detailed understanding of the promenade and coastline.

But in several locations the teams hit harder-than-anticipated ground conditions, so they had to change their approach and find other ways to gather the information safely.

And then the weather.

The agency says recent stormy weather added to the disruption, and calls the result “a short delay to the programme”.

Seafront compound to go in December
Once the last investigations finish, the agency will take its machinery and equipment off the seafront and clear the site compound.

It expects to complete that work, which it calls site demobilisation, by the end of the week commencing 14th December 2026.

Teams will stay on site over the coming weeks as this phase of the project draws to a close.

Project office shuts for winter
The agency says it closed the public project office in Ventnor because winter brings fewer visitors and the investigations have reached their final stages.

The Environment Agency said,

“Don’t worry, we’re still here to help.”

People can still email the project team at [email protected], and the agency will keep posting updates on its project information page.

It thanked everyone who called in at the office over recent months to ask questions and give their views on the scheme.

The agency says it is already planning more chances in the New Year for people to meet the team and give their feedback.

Castle Cove path due to reopen by 27th November
Part of the coastal path at Castle Cove remains closed while the agency continues developing the scheme.

The agency said it would reopen the path for weekend access from Friday afternoon, 20th November, until Monday morning, 23rd November.

It expects to fully reopen the path by 27th November 2026.