Busy road closed for three weeks for bridge strengthening works

In order to continue carrying any traffic larger than a Transit van, the bridge needs to be strengthened

godshill bridge

A major scheme to strengthen a bridge that supports the main road on the approach to Godshill is to begin later this month.

The work to Bow Bridge will ensure the busy A3020 Newport Road can continue to carry all traffic. Without strengthening, a 7.5 tonne restriction would be required meaning the road could not be used by vehicles over that weight – essentially, nothing larger than a Transit-sized van.

The project will involve digging the road out over the bridge to reveal the top of the masonry arch, waterproofing the stonework and then backfilling the void with concrete. This will provide greater support than the current clay-rich soil. Lastly, the highway surface will be reinstated.

Closed for three weeks
Because of the busy nature of the A3020, the work is being scheduled for a time of the year well outside the holiday season.

It will however be necessary to close the road to all traffic for a planned three-week period beginning on 27th January.

Hodson: “Not feasible to undertake the work in phases”
Ian Hodson, Island Roads structures manager, said:

“Because of the narrow width of this listed bridge it is unfortunately not feasible to undertake the work in phases by closing one lane at a time as we were able to at School Green Road bridge in Freshwater recently.

“A full road closure will therefore be necessary, but we have scheduled the work for what is the quietest time of the year in order to minimise disruption.

“While the planned works are for three weeks, which will allow the road to be re-opened before the February half-term break, we will be applying for a four-week closure to provide a week’s contingency in case of bad weather or other unforeseen problems.”

During the closure, the diversion route will be from Whiteley Bank via Canteen Road, Apse Heath and Arreton to Blackwater. It is proposed to have on-street parking restrictions on Ventnor Road, Apse Heath, to prevent traffic backing up to the Apse Heath roundabout.

Businesses in Godshill and Rookley will shortly receive a letter explaining more about the work.


News shared by Gavin on behalf of Island Roads. Ed

Friday, 10th January, 2020 4:40pm

By

ShortURL: http://wig.ht/2noV

Filed under: Godshill, Isle of Wight News, Roads, Top story, Travel

Any views or opinions presented in the comments below must comply with the Commenting 'House Rules' and are solely those of the author and do not represent those of OnTheWight.

Leave your Reply

1 Comment on "Busy road closed for three weeks for bridge strengthening works"

newest oldest most voted
mariner58

It will obviously cause tremendous disruption but nothing lasts forever and it needs to be done but banning parking on Ventnor Road is rather pointless without also, rigorously, banning hedge trimming, scaffolding, Southern Water, SGN ( in fact all utilities ) and most of all Wight Fibre from being anywhere near any part of the detour route!