Isle of Wight roadworks or road closures starting today or tomorrow. Information provided by Elgin via Roadworks.org

A3020 Blackwater Road, Newport, Isle Of Wight
16 December — 18 December Traffic control (Stop/Go boards)
Delays likely due to Streetworks
Install N? 2 Lanterns (N? 2 Columns) Newport at Newport: At The Junction Of Shide Road & Blackwater Road (Ml 410022):
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

A3020 St Georges Way, Newport, Isle Of Wight
16 December — 18 December Traffic control (Stop/Go boards)
Delays likely due to Streetworks
Install No 23 Lanterns (No 22 Columns) 3 X 40mph Signs, 3 Warning Signs, 1 Public Notice And 1 Lit Vehicle Activation Sign Newpor at Newport: From Column 27, South To Junction Of Shide Road (Ml 210001, Ml 210002, Ml 210003 And Ml 210004): :; Sl Cip Sche
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

A3054 Binstead Hill, Binstead, Isle Of Wight
17 December — 19 December Traffic control (multi-way signals)
Delays likely due to Streetworks
P/H That Keeps Breaking Out – Requires A Patch .50 X .35 X 30mm Patch 2.2 X 1.3 X 50/100mm Tm – Suggested Four Way Temp Lights (Cw: Pothole) H1 Urban Binstead at Binstead: On Binstead Hill On Wootton Bound Side Of The C/Way Just Before The Mini Roundabout: Binstead Hill-Binstead
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Roseway, Lake, Isle Of Wight
16 December — 18 December Road closure
Delays likely due to Streetworks
– Replace Cover And Frame In Carriageway at 26 Roseway Lake
Responsibility: Southern Water
EToN status: Advanced planning

A3020/A3054 Parkhurst Road, Newport, Isle Of Wight
16 December — 22 December Some carriageway incursion
Delays possible due to Streetworks
– Install Fire Hydrant In Layby. at 2 Horsebridge Hill, Newport, Isle Of Wight.
Responsibility: Southern Water
EToN status: Advanced planning

A3020 Shanklin Road, Godshill, Isle Of Wight
17 December — 19 December Traffic control (two-way signals)
Delays possible due to Streetworks
C/W Ridege And Depression (Suspected Wheelpush). Lengthways Along C/W. Measures 4.25 Metres X 0.5 Metres On West Bound C/W Near Centre Line. Up To 60 Mm Above General Road Surface Needs Saw Cut. Tm Best Done At Night. 2way Lights. (Cw: Pothole) H1 Urban Godshill at Godshill: On The “S” Bend After The Gulf Petrol Station. Opp Barrow Cottage.: Shanklin Road-Godshill
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

A3055 East Hill Road, Ryde, Isle Of Wight
17 December — 19 December Traffic control (multi-way signals)
Delays possible due to Streetworks
Sawcut And Infill P/H’S X 2 One On Nearside Tyreline And The Other On The Offside Tyreline ,45 X .35 X 50mm .60 X .60 X 40mm Tm – Suggested Four Way Temp Lights (Cw: Pothole) H1 Urban Ryde at Ryde: On The Sandown Bound Side Of The C/Way O/S Rougemont Flats, Easthill Road, Ryde: East Hill Road-Ryde
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

A3055 Esplanade, Ryde, Isle Of Wight
17 December — 19 December Lane closure
Delays possible due to Streetworks
Idr – Ironwork Cover Breaking Out Requires Resetting 1.80 X 1.20 X 50/100mm Tm – Lane Closure Ryde at Ryde: On The Roundabout At The End Of The Esplanade On The Inside Sandown Bound Lane: Esplanade-Ryde
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

B3399/B3401 Freshwater Road, Shalfleet, Isle Of Wight
17 December — 17 December Traffic control (two-way signals)
Delays possible due to Streetworks
Access Required To Underground Bt Structure To Provide Service – No Structural Changes. Work Being Carried Out On Existing Bt Plant at Freshwater Road Near The Junction Of Dodpits Lane And Brook Road Shalfleet Po41 0ud
Responsibility: BT
EToN status: Advanced planning

B3399 Brighstone Road, Brook, Isle Of Wight
16 December — 17 December Traffic control (two-way signals)
Delays possible due to Streetworks
313495 Brook – Fpc – Fibre Path Clearance – Interim To Permanent Reinstatement at In C/W Approx 45m West Of Jnc Church Lane O/S Church Of St Peter & St Paul Mottistone
Responsibility: BT
EToN status: Advanced planning

B3399 Brook Road, Brighstone, Isle Of Wight
16 December — 17 December Traffic control (two-way signals)
Delays possible due to Streetworks
Brightstone – 315409 Seg Ref: Smjbri444 – Interim To Permanent Reinstatement at Approx 43m West Entrance Petite Place, Brook Road, Brighstone, Iow
Responsibility: BT
EToN status: Advanced planning

B3399 Limerstone Road, Brighstone, Isle Of Wight
16 December — 17 December Traffic control (two-way signals)
Delays possible due to Streetworks
Brightstone – 313495 – Bduk – Fpc – Fibre Path Clearance – Interim To Permanent Reinstatement at 74m E Limerstone Cottage
Responsibility: BT
EToN status: Advanced planning

B3399 Main Road, Brighstone, Isle Of Wight
16 December — 17 December Traffic control (two-way signals)
Delays possible due to Streetworks
Shanklin – 317888 Jg030 Fpc – Interim To Permanent Works In Carriageway at In C/W O/S Shelley & Brierley, Main Road
Responsibility: BT
EToN status: Advanced planning

B3399 Main Road, Brighstone, Isle Of Wight
16 December — 17 December Traffic control (two-way signals)
Delays possible due to Streetworks
Shanklin – 317888 Jg029 Interim To Permanent Works In Carriageway at In C/W Os Pastures, Chiltern Lane, On Main Road, Brighstone
Responsibility: BT
EToN status: Advanced planning

B3401 Shide Road, Newport, Isle Of Wight
16 December — 18 December Traffic control (Stop/Go boards)
Delays possible due to Streetworks
Install No 17 Lanterns (No 17 Columns) Newpor at Newport: From Blackwater Road, West To Whitepit Lane (Ml 230106, 230105 And Ml 230104): :; Sl Cip Scheme Sl Cip Scheme
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Esplanade, Sandown, Isle Of Wight
16 December — 18 December Traffic control (Stop/Go boards)
Delays possible due to Streetworks
Install N? 44 Lanterns (N? 24 Columns) 1 No Waiting Sign, 2 Route/Direction Signs, 2 Parking Restriction Signs, 8 Resident Parking Permit Signs, 4 Warning Signs, 1 Lit Warning Sign & 22 Festive Decorations Sandown at Sandown: From Revetment, North East To Avenue Slip (Ml 440198, Ml 440199, Ml 440459 & Ml 441200):
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Sandy Lane, Shanklin, Isle Of Wight
17 December — 19 December Traffic control (multi-way signals)
Delays possible due to Streetworks
Idr – Ironwork Breaking Out Leaving A 30mm Exposed Edge Reset Gully Cover Tm – Suggested Three Way Temp Lights (Cw: Irnwk Not Exceed +Or- 20mm) Shanklin at Shanklin: Jnc Of Cedar Drive And Whitecross Lane: Sandy Lane-Shanklin
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

St James Square, Newport, Isle Of Wight
16 December — 18 December Traffic control (Stop/Go boards)
Delays possible due to Streetworks
Install N? 7 Lanterns (N? 1 Column) Newport at Newport: From Junction Of High Street, South To Junction Of Pyle Street (Ml 220078):
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Albion Road, Sandown, Isle Of Wight
16 December — 24 December Some carriageway incursion
Delays unlikely due to Streetworks
Lay New Main From Nearside Carriageway To Site at Adj 97 – 101 High Street
Responsibility: SGN
EToN status: Advanced planning

B3325 High Street, Cowes, Isle Of Wight
16 December — 18 December Traffic control (give & take)
Delays unlikely due to Streetworks
Lift The Manhole Cover To The Combined Sewer Overflow To Install Monitoring Equipment. No Excavation at Adj To 73 High Street
Responsibility: Southern Water
EToN status: Advanced planning

B3325 High Street, Cowes, Isle Of Wight
16 December — 31 December Some carriageway incursion
Delays unlikely due to Streetworks
Excavation Of Footway And Carriageway To Install New Electrical Supplies To New Flats At Site Of Waterside Public House. This Is A One Way Road, Traffic Management Not Required – We Will Maintain Min Clearances For Types Of Vehicles Using This Road. at O/S 71 To 74
Responsibility: Southern Electric
EToN status: Advanced planning

Niton Road, Godshill, Isle Of Wight
16 December — 17 December Some carriageway incursion
Delays unlikely due to Streetworks
Chale Green 324495 Overlay – Lay Approx 15m Of Duct 54 In Verge To Link Existing Bt Boxes To Facilitate Spine Cabling Works. at So Leechmore Farm, Niton Road, Junc Of Beacon Alley, Godshill
Responsibility: BT
EToN status: Advanced planning

Car Park Quay Road, Ryde, Isle Of Wight
16 December — 31 December Some carriageway incursion
Delays unlikely due to Streetworks
Scaffold (Island Scaffold) at O/S Ice Rink
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Gregory Close, Nettlestone, Isle Of Wight
16 December — 18 December No carriageway incursion
Delays unlikely due to Streetworks
Install 2m Of 1 Way Poly Duct In Footway at O/S 6 , Gregory Close
Responsibility: BT
EToN status: Advanced planning

Monks Brook, Newport, Isle Of Wight
17 December — 21 December Some carriageway incursion
Delays unlikely due to Streetworks
Install 1m Of 1 Way Poly Duct In Footway at 83m North East From Junc Dodnor Lane, Monks Brook
Responsibility: BT
EToN status: Advanced planning

Rew Lane, Wroxall, Isle Of Wight
17 December — 18 December Traffic control (give & take)
Delays unlikely due to Streetworks
Installation Of Asphalt Hump To Prevent Flooding Wroxall at Wroxall: Ml 540226, Outside Span Farm: Rew Lane-Wroxall
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Image: Oatsy40under CC BY 2.0