Road closures and road works: 27th February 2014

For details of week’s road closures and road works see our weekly update.

Road cones:Long term closures (non flooding):

Cliff Path, Lake – closed to vehicles due to safety reasons
Cliff Path, Lake – closed to pedestrians from Winchester house car park to Skew Bridge path / Lake Cliff Gardens due to safety reasons
Cliff Path, Shanklin – closed to pedestrians between Delphi Road and St Boniface Cliff Road due to safety reasons
Knighton Lane & Knighton Shute, Newchurch – closed due to a poor surface (these roads will remain closed until the area dries out as the proposed surface treatment cannot be applied while the roads are wet)
Rew Lane, Ventnor – closed due to a poor surface
Undercliff Drive, Niton – between Mirables (in the west) and Seven Sisters Road (in the east) – closed for safety reasons
Undercliff Drive, Niton – between from Inglewood Park to a point west where it meets Seven Sisters Road – closed due to flooding.

Roadworks starting today or tomorrow

A3020/A3054 Parkhurst Road, Newport, Isle Of Wight
27 February — 27 February
Delays likely Lane closure
Works location: Newport: As You Approach St Mary’S Hospital On Your Left And On The Slip Road: 2nd Past Lonsdale Av
Works description: Lamp: Outage (Single Unit) – Numbers 31, 32 And 35 (Enquiry 16022468) (Sl: Outage (Single Unit))
Responsibility for works: Island Roads on behalf of the Isle of Wight Council

A3020 High Street, Godshill, Isle Of Wight
27 February — 03 March
Delays likely Traffic control (Stop/Go boards)
Works location: Godshill: Next To Jasmine Cottage. Large Pothole To Side Of Southbound C/W. In Wheel Line.: High Street-Godshill
Works description: Repair C/W Pothole Measures 850 X 450 X 75mm Depth.
Responsibility for works: Island Roads on behalf of the Isle of Wight Council

A3054 Binstead Hill, Binstead, Isle Of Wight
28 February — 04 March
Delays likely Traffic control (two-way signals)
Works location: Binstead Hill/Road Jcn With Newnham Road Working Eastward And Finishing At Stone Pits Close
Works description: Recovery Of Openreach Cable Using 2 Way Rolling Traffic Lights With No Excavation
Responsibility for works: BT

A3054 Elenors Grove, Binstead, Isle Of Wight
28 February — 04 March
Delays likely Traffic control (two-way signals)
Works location: Start At Ellenors Grove Jcn With Fisnbourn Lane And Finishing At Start Of Quarr Hill
Works description: Recovery Of Openreach Cable Using 2 Way Rolling Traffic Lights With No Excavation
Responsibility for works: BT

A3054 Quarr Hill, Binstead, Isle Of Wight
28 February — 04 March
Delays likely Traffic control (two-way signals)
Works location: Start On Quar Hill (Finish Of Ellenors Grove) And Continuing Along To And Finishing At Jcn With Newham Road
Works description: Recovery Of Redundant Openreach Cable Using 2 Way Rolling Traffic Lights With No Excavation
Responsibility for works: BT

A3055 High Street, Shanklin, Isle Of Wight
28 February — 03 March
Delays likely Traffic control (Stop/Go boards)
Works location: Shanklin: Outside The Natwest Bank, On The Bank Side Of The Road.: High Street-Shanklin
Works description: Pothole In Road – Place Out Barriers And Set Up Traffic Managment For Void. (Enquiry 16021802) (Cw: Pothole)
Responsibility for works: Island Roads on behalf of the Isle of Wight Council

A3055 High Street, Shanklin, Isle Of Wight
28 February — 04 March
Delays likely Traffic control (Stop/Go boards)
Works location: Shanklin: Outside The Natwest Bank, On The Bank Side Of The Road.: High Street-Shanklin
Works description: Pothole In Road -Sub Con Hss. Place Out Barriers And Set Up Traffic Managment For Void. (Enquiry 16021802) (Cw: Pothole)
Responsibility for works: Island Roads on behalf of the Isle of Wight Council

Skinners Hill, Newchurch, Isle Of Wight
28 February — 11 March
Delays likely Road closure
Works location: Newchurch: From Hill Farm Entrance 250m West (Ml440435): Skinners Hill-Newchurch
Works description: Carriageway Reconstruction, Planing And Resurfacing. (Ff-Stren100:R/H4, Strengthen 30mm Fibrovia And 70mm Foambase-Rural:H4) Newchu
Responsibility for works: Island Roads on behalf of the Isle of Wight Council

A3020 School Road, Godshill, Isle Of Wight
27 February — 03 March
Delays possible Traffic control (Stop/Go boards)
Works location: Godshill: Main Road Between School Crescent And Entrance To Godshill Village. Several Large Potholes
Works description: Please Fill 2 Large Potholes No Need For Saw Cut Edges
Responsibility for works: Island Roads on behalf of the Isle of Wight Council

A3054 Fairlee Road, Newport, Isle Of Wight
28 February — 13 March
Delays possible Traffic control (multi-way signals)
Works location: Newport: (Binfield Corner) From Racecourse South West To Fairlee Road (Ml 210055):
Works description: Install No 8 Lanterns (No 8 X 8m Columns) 1 Lead+Socket And 1 Route/Direction Sign
Responsibility for works: Island Roads on behalf of the Isle of Wight Council

B3328 Queens Road, Shanklin, Isle Of Wight
28 February — 04 March
Delays possible Traffic control (Stop/Go boards)
Works location: Shanklin: Medhamsted Hotel And Havelock Hotel: Queens Road-Shanklin
Works description: Idr 0.3×0.3x40mm And 0.3×0.25x40mm, Tm=Give And Take
Responsibility for works: Island Roads on behalf of the Isle of Wight Council

Gate Lane, Freshwater, Isle Of Wight
28 February — 04 March
Delays possible Traffic control (Stop/Go boards)
Works location: Freshwater: Gate Lane-Freshwater, Vehicle Entrance To Iwc Car Park.: Gate Lane-Freshwater
Works description: Idr, A 13m X 2.2m Patch Is Required To Repair The Vehicle Crossing Across The Footway To The Iwc Aacar Park. Tm= Work From Car Park, Shut Entrance And Unlock And Remove Post From Secondary Entrance.
Responsibility for works: Island Roads on behalf of the Isle of Wight Council

Regent Street, Shanklin, Isle Of Wight
28 February — 04 March
Delays possible Traffic control (Stop/Go boards)
Works location: Shanklin: Jo Atherley Road: Regent Street-Shanklin
Works description: Idr 0.3×0.25×40, 025×0.2×40 0.3×0.2×40 And 0.5 X0.55x60mm, Stop/Go
Responsibility for works: Island Roads on behalf of the Isle of Wight Council

Copse Lane, Freshwater, Isle Of Wight
28 February — 04 March
Delays possible Traffic control (Stop/Go boards)
Works location: Freshwater: Copse Lane-Freshwater Footway, O/S A Property Called Sailor Cottage.: Copse Lane-Freshwater
Works description: Idr , The Concrete Vehicle Crossing Is Very Broken Up, Please Relay. 5m X 1.3m. Tm = Alternative/Temporary Footway, Parking Should Be Suspended Both Sides Of Crossing And House Owner To Be Advised.
Responsibility for works: Island Roads on behalf of the Isle of Wight Council

Hooke Hill, Freshwater, Isle Of Wight
28 February — 04 March
Delays possible Traffic control (Stop/Go boards)
Works location: Freshwater: Hookehill,Freshwater On Footway O/S A Property Called Kingsleigh.: Hooke Hill-Freshwater
Works description: Rut On Bitmac Footway, 440mm X 320mm X 25mm Deep, Tm= Footway Is Wide Enough To Remain Open. (Fw: Fw/Cyclep Rut)
Responsibility for works: Island Roads on behalf of the Isle of Wight Council

Carter Avenue, Shanklin, Isle Of Wight
28 February — 04 March
Delays possible Traffic control (Stop/Go boards)
Works location: Shanklin: O/S No. 56: Carter Avenue-Shanklin
Works description: Idr – 2 X P/H’S Bordering An Old Reinstatement Causing A Ridge Patch Req’D To Cover Both Holes .80 X .50 Tm – F/Way Only
Responsibility for works: Island Roads on behalf of the Isle of Wight Council

Freshwater Footpath 59, Freshwater, Isle Of Wight
28 February — 04 March
Delays possible Traffic control (Stop/Go boards)
Works location: Freshwater: O/S The Albion Hotel, Freshwater Bay, By The Parking Area Next To The Sea Wall.: Freshwater Footpath 59-Fre
Works description: Priority Please. Two Pot Holes, 1:- 420mm X 570mm X 85mm Deep, 2:- 300mm X 280mm X 50mm, Tm =Gandt . (Cw: Pothole)
Responsibility for works: Island Roads on behalf of the Isle of Wight Council

Landguard Manor Road, Shanklin, Isle Of Wight
28 February — 04 March
Delays possible Traffic control (Stop/Go boards)
Works location: Shanklin: Os N Opp 34, 43: Landguard Manor Road-Shanklin
Works description: Idr 0.3×0.3×50 And 0.4×0.3×60, Tm=Give And Take
Responsibility for works: Island Roads on behalf of the Isle of Wight Council

Palmerston Road, Shanklin, Isle Of Wight
28 February — 04 March
Delays possible Traffic control (Stop/Go boards)
Works location: Shanklin: Harrow Lodge,: Palmerston Road-Shanklin
Works description: Idr, Tm=Give And Take, 2.1×0.2x25mm F/W Pothole
Responsibility for works: Island Roads on behalf of the Isle of Wight Council

Image: Natesh Ramasamy under CC BY 2.0