Road closures and road works: 6th March 2014

For details of week’s road closures and road works see our weekly update.

Long term closures (non flooding):

Cliff Path, Lake – closed to vehicles due to safety reasons
Cliff Path, Lake – closed to pedestrians from Winchester house car park to Skew Bridge path / Lake Cliff Gardens due to safety reasons
Cliff Path, Shanklin – closed to pedestrians between Delphi Road and St Boniface Cliff Road due to safety reasons
Hill Place Lane – closed to vehicles due to safety reasons
Knighton Lane & Knighton Shute, Newchurch – closed due to a poor surface (these roads will remain closed until the area dries out as the proposed surface treatment cannot be applied while the roads are wet)
Rew Lane, Ventnor – closed due to a poor surface
Undercliff Drive, Niton – between Mirables (in the west) and Seven Sisters Road (in the east) – closed for safety reasons

Roadworks starting today or tomorrow

Palmers Lane, Newchurch, Isle Of Wight
06 March — 13 March
Delays likely Road closure
Works location: Newchurch: From Winford Road 457m East (Ml440433): Palmers Lane-Newchurch
Works description: Carriageway Reconstruction, Planing And Resurfacing. (Ff-Stren100:U/H4, F1-Strengthen 30mm Fibrovia And 70mm Foambase-Urban:H4) Newchu
Responsibility for works: Island Roads on behalf of the Isle of Wight Council

A3054 Binstead Road, Ryde, Isle Of Wight
07 March — 07 March
Delays possible Traffic control (two-way signals)
Works location: Ryde: Below Lampost No 44: Binstead Road-Ryde
Works description: Reset Rocking Gully Frame And Cover. Tm=Two Way Temp Traffic Lights. (Gl: Ironwork Rocking/Corrosion) Ryde
Responsibility for works: Island Roads on behalf of the Isle of Wight Council

B3399 Limerstone Road, Shorwell, Isle Of Wight
06 March — 10 March
Delays possible Traffic control (two-way signals)
Works location: West Court Farm Cottage, Limerstone Road
Works description: Perm Reinstratement Of Tar C/Way ***2-Way Lights Required***
Responsibility for works: Southern Water

Rew Street, Gurnard, Isle Of Wight
07 March — 20 March
Delays possible Traffic control (two-way signals)
Works location: Gurnard: Eastern Verge To The North Of ‘Flora Rosa’: Rew Street-Gurnard
Works description: Infill Of Highway Verge With Topsoil (12.5 M3). Re-Seeding Of Verge (25 Sqm). Installation Of 7 Hazard Markers. 130m Of 100mm White Lining At Edge Of Carriageway. Tm = 2 Way Lights Gurnar
Responsibility for works: Island Roads on behalf of the Isle of Wight Council
Current status: Advanced planning