Road closed works and traffic lights

Roadworks and road closures: 18th June 2015

Check our weekly list of roadworks and road closures for more precise details of when works will start in your area.

Roadworks or road closures starting today or tomorrow. Information provided by Elgin via Roadworks.org

A3020 Newport Road, Godshill, Isle Of Wight
19 June — 19 June Traffic control (two-way signals)
Delays possible due to Streetworks
Access Required To Underground Bt Structure To Restore Service – No Structural Changes. Work Being Carried Out On Existing Bt Plant at Outside 12 Newport Road Godshill Isle Of Wight Po38 3hr
Responsibility: BT
EToN status: Advanced planning

A3054 Bridge Road, Yarmouth, Isle Of Wight
18 June — 01 July Traffic control (give & take)
Delays unlikely due to Streetworks
Install N? 2 Lanterns (N? 2 Columns) Yarmouth at Yarmouth: From The Junction Of St James Street, West To Column 5 (Ml 640292):
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

A3055 Marlborough Road, Ryde, Isle Of Wight
18 June — 01 July No carriageway incursion
Delays unlikely due to Streetworks
Excavate In Footway For New Electric Service at O/S 131 Marlborough Rd
Responsibility: Southern Electric
EToN status: Advanced planning

A3055 Sandown Road, Lake, Isle Of Wight
18 June — 22 June No carriageway incursion
Delays unlikely due to Streetworks
Excavate And Remove Royal Mail Pouchbox at Pedestal In Pavement. Near The Junction Of Sandown Rd & Newport Rd. Near The Po.
Responsibility: Romec Ltd
EToN status: Advanced planning

Alexandra Road, Shanklin, Isle Of Wight
19 June — 23 June No carriageway incursion
Delays unlikely due to Streetworks
Excavate And Remove Royal Mail Pouchbox at Pedestal In Pavement. On The Junction Of Alexandra Rd & Palmerston Rd
Responsibility: Romec Ltd
EToN status: Advanced planning

B3328 Chine Avenue, Shanklin, Isle Of Wight
19 June — 23 June No carriageway incursion
Delays unlikely due to Streetworks
Excavate And Remove Royal Mail Pouchbox at Pedestal In Grass. Near The Junction Of Chine Ave & Queens Rd.
Responsibility: Romec Ltd
EToN status: Advanced planning

B3328 Queens Road, Shanklin, Isle Of Wight
19 June — 23 June No carriageway incursion
Delays unlikely due to Streetworks
Excavate And Remove Royal Mail Pouchbox at Pedestal In Pavement. On The Junction Of Queens Rd & Clarendon Rd.
Responsibility: Romec Ltd
EToN status: Advanced planning

B3395 High Street, Bembridge, Isle Of Wight
18 June — 02 July Some carriageway incursion
Delays unlikely due to Streetworks
Scaffold (Thf Scaffolding) at O/S Pomegranate, 37
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Bridge Road, East Cowes, Isle Of Wight
18 June — 22 June Traffic control (give & take)
Delays unlikely due to Streetworks
Footway Re Construction And Surfacing (Fwl: Slabs 50%Patch)) East Cowes at East Cowes: Link Footway From Ferry Road To Bridge Road (Ml F10101): Bridge Road-East Cowes
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Queens Road, Freshwater, Isle Of Wight
18 June — 26 June Traffic control (give & take)
Delays unlikely due to Streetworks
Relay Service From Mid Carriageway To Site at Os Hill House
Responsibility: SGN
EToN status: Advanced planning

The Mall, Brading, Isle Of Wight
18 June — 22 June No carriageway incursion
Delays unlikely due to Streetworks
Excavate And Remove Royal Mail Pouch Box at Pedestal In Grass, Edge Of Pavement On The Mall
Responsibility: Romec Ltd
EToN status: Advanced planning

Atherley Road, Shanklin, Isle Of Wight
19 June — 23 June No carriageway incursion
Delays unlikely due to Streetworks
Excavate And Remove Royal Mail Pouchbox at Pedestal In Pavement. On The Junction Of Atherley Rd & Regent St. Next To Pillarbox.
Responsibility: Romec Ltd
EToN status: Advanced planning

High Street, Yarmouth, Isle Of Wight
18 June — 01 July Traffic control (give & take)
Delays unlikely due to Streetworks
Install N? 7 Lanterns (N? 2 Columns, 2pb’S & 1wb) Yarmouth at Yarmouth: From The Square, East To End Column (Ml 640292, Ml 640293 & Ml 640296):
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

St James Street, Yarmouth, Isle Of Wight
18 June — 01 July Traffic control (give & take)
Delays unlikely due to Streetworks
Install N? 3 Lanterns (N? 1 Column) Yarmouth at Yarmouth: From Tennyson Road, North To Bridge Road (Ml 640292 & Ml 640294):
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

St Boniface Cliff Road, Shanklin, Isle Of Wight
18 June — 22 June No carriageway incursion
Delays unlikely due to Streetworks
Excavate And Remove Royal Mail Pouchbox at Pedestal In Grass. On The Juction Of St Boniface Cliff Rd & Northcliff Gdn. Partially Hidden By Hedge
Responsibility: Romec Ltd
EToN status: Advanced planning

Quay Street, Yarmouth, Isle Of Wight
18 June — 01 July Traffic control (give & take)
Delays unlikely due to Streetworks
Install N? 1 Lantern (N? 1 Wb) Yarmouth at Yarmouth: From The Square, West To Single Wall Bracket (Ml 640332):
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Flitcroft Gardens, Lake, Isle Of Wight
18 June — 22 June No carriageway incursion
Delays unlikely due to Streetworks
Excavate And Remove Royal Mail Pouchbox at Pedestal In Grass. On The Junction Of Flitcroft Gardens & Sandown Rd. Partially Hidden By Hedge.
Responsibility: Romec Ltd
EToN status: Advanced planning

Gordon Road, Cowes, Isle Of Wight
18 June — 26 June Some carriageway incursion
Delays unlikely due to Streetworks
Alteration Of Gas Supply From Nearside Footway To Site at Outside Number 7
Responsibility: SGN
EToN status: Advanced planning

Hope Road, Shanklin, Isle Of Wight
19 June — 23 June No carriageway incursion
Delays unlikely due to Streetworks
Excavate And Remove Royal Mail Pouchbox at Pedestal In Pavement. On The Junction Of Hope Rd & Queens Rd.
Responsibility: Romec Ltd
EToN status: Advanced planning

Lake Green Road, Lake, Isle Of Wight
18 June — 22 June No carriageway incursion
Delays unlikely due to Streetworks
Excavate And Remove Royal Mail Pouchbox at Pedestal In Pavement. On The Junction Of Lake Green Rd & Percy Road.
Responsibility: Romec Ltd
EToN status: Advanced planning

Lamorbey Road, Lake, Isle Of Wight
18 June — 22 June No carriageway incursion
Delays unlikely due to Streetworks
Excavate And Remove Royal Mail Pouchbox at Pedestal In Pavement. On The Junction Of Lamorbey Rd & Newport Rd. Adjacent To The Spar.
Responsibility: Romec Ltd
EToN status: Advanced planning

Mill Street, Newport, Isle Of Wight
18 June — 01 July Traffic control (give & take)
Delays unlikely due to Streetworks
Install N? 3 Lanterns (N? 3 Columns) 1 Route/Direction Sign & 1 Lit Warning Sign Newport at Newport: From High Street, North To Junction Of Crocker Street (Ml 240167):
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Osborne Road, Shanklin, Isle Of Wight
19 June — 23 June No carriageway incursion
Delays unlikely due to Streetworks
Excavate And Remove Royal Mail Pouchbox at Pedestal In Pavement. On The Junction Of Osborne Rd & Queens Rd. Near A Pillarbox.
Responsibility: Romec Ltd
EToN status: Advanced planning

Parkway, Binstead, Isle Of Wight
18 June — 22 June Traffic control (give & take)
Delays unlikely due to Streetworks
Footway Re Construction And Surfacing (Fwl: Bit Partrecon Fwr: Bit Partrecon) Binstead at Binstead: Whole Length Of Footway From Verwood Drive To The Mall (Ml 340641): Parkway-Binstead
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Scarrots Lane, Newport, Isle Of Wight
18 June — 01 July Traffic control (give & take)
Delays unlikely due to Streetworks
Install N? 4 Lanterns (N? 1 Column & 3 Wb’S) 1 Warning Sign Newport at Newport: From St James Street Upper, West To New Street (Ml 240360):
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Shore Road, Gurnard, Isle Of Wight
18 June — 22 June Traffic control (give & take)
Delays unlikely due to Streetworks
Footway Re Construction And Surfacing (Fwl: Bit Fullrecon Fwr: Bit Partrecon) Gurnard at Gurnard: From Shore Road To No 15 Princes Esplanade (Ml 130114): Shore Road-Gurnard
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Solent View Road, Nettlestone, Isle Of Wight
19 June — 23 June Traffic control (give & take)
Delays unlikely due to Streetworks
Footway Re Construction And Surfacing (Fwl: Bit Partrecon Fwr: Bit Partrecon) Nettlestone at Nettlestone: From Greenham Drive 250m East (Ml 340564): Solent View Road-Nettlestone
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

South Street, Ryde, Isle Of Wight
19 June — 26 June Some carriageway incursion
Delays unlikely due to Streetworks
Gsmr/Hse Cut Off 42095 at Os 4
Responsibility: SGN
EToN status: Advanced planning

St Cross Lane, Newport, Isle Of Wight
18 June — 01 July Traffic control (give & take)
Delays unlikely due to Streetworks
Install N? 1 Lantern (N? 1 Column) 2 Route/Direction Signs Newport at Newport: From Crocker Street, North To Column 3 (Ml 220148):
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

St Martins Avenue, Shanklin, Isle Of Wight
18 June — 22 June No carriageway incursion
Delays unlikely due to Streetworks
Excavate And Remove Royal Mail Pouchbox at Pedestal In Pavement. Near The Junction Of St Martins Ave & Arthurs Hill
Responsibility: Romec Ltd
EToN status: Advanced planning

St Pauls Avenue, Shanklin, Isle Of Wight
19 June — 23 June No carriageway incursion
Delays unlikely due to Streetworks
Excavate And Remove Royal Mail Pouchbox at Pedstal In Pavement. On The Junction Of St Pauls Ave & Spring Gardens.
Responsibility: Romec Ltd
EToN status: Advanced planning

Sun Hill, Cowes, Isle Of Wight
18 June — 25 June Some carriageway incursion
Delays unlikely due to Streetworks
Scaffold (Upright Scaffold) at O/S 43
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

The Fairway, Lake, Isle Of Wight
18 June — 22 June No carriageway incursion
Delays unlikely due to Streetworks
Excavate And Remove Royal Mail Pouchbox at Pedestal In Tarmac Pavement, Outside Of No. 14 The Fairway At Junction Of The Fairway And Medeway
Responsibility: Romec Ltd
EToN status: Advanced planning

The Fairway, Lake, Isle Of Wight
18 June — 22 June No carriageway incursion
Delays unlikely due to Streetworks
Excavate And Remove Royal Mail Pouchbox at Pedestal In Grass, Next To Postbox, Outside 66 The Fairway, At Junction Of The Fairway And Roseway
Responsibility: Romec Ltd
EToN status: Advanced planning

The Fairway, Lake, Isle Of Wight
19 June — 23 June No carriageway incursion
Delays unlikely due to Streetworks
Excavate And Remove Royal Mail Pouchbox at Pedestal In Pavement. On The Junction Of The Fairway & Medeway.
Responsibility: Romec Ltd
EToN status: Advanced planning

The Mall, Binstead, Isle Of Wight
18 June — 22 June Traffic control (give & take)
Delays unlikely due to Streetworks
Footway Re Construction And Surfacing (Fwl: Bit Partrecon Fwr: Bit Part Recon) Binstead at Binstead: From Greenway To Parkway (Ml 340625): The Mall-Binstead
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Venner Avenue, Northwood, Isle Of Wight
19 June — 23 June No carriageway incursion
Delays unlikely due to Streetworks
Excavate And Remove Royal Mail Pouchbox at In Tarmac, Junction Of Venner Ave, Horseshoe Close Next To Road Name Sign
Responsibility: Romec Ltd
EToN status: Advanced planning

Webster Way, Newchurch, Isle Of Wight
19 June — 23 June Traffic control (give & take)
Delays unlikely due to Streetworks
Footway Re Construction And Surfacing (Fwl: Bit Partrecon Fwr: Bit Partrecon) Newchurch at Newchurch: Whole Length Of Footway From Youngwoods Way (Ml 441443): Webster Way-Newchurch
Responsibility: Island Roads on behalf of the Isle of Wight Council
EToN status: Advanced planning

Woodvale Road, Gurnard, Isle Of Wight
19 June — 23 June No carriageway incursion
Delays unlikely due to Streetworks
Excavate And Remove Royal Mail Pouchbox at In Grass, Corner Of Woodvale Road/Cow Lane
Responsibility: Romec Ltd
EToN status: Advanced planning

Woodvale Road, Gurnard, Isle Of Wight
19 June — 23 June No carriageway incursion
Delays unlikely due to Streetworks
Excavate And Remove Royal Mail Pouch Box at In Grass, Corner Of Woodvale Road/Cow Lane
Responsibility: Romec Ltd
EToN status: Advanced planning

Image: ell-r-brown under CC BY 2.0