Letter: Asphalt plant: Credibility of soil investigation challenged

We always welcome a Letter to the Editor to share with our readers. A popular subject in recent weeks has been issues surrounding the proposed asphalt plant. This letter from one reader calling himself Harvey. Ed


In recent weeks I wrote to Mr Murphy (LPA) outlining my concerns of the potential shortcomings of the current soils investigations. It would appear that my concerns have been disregarded and not brought to the attention of the Environment Agency (EA) or IWC consultants.

I have been asked to accept that because the EA have had sight of the proposals and not raised any concerns no further action need be taken.

Boreholes
I would confidently assert that while IWC consultants and the EA have reviewed the applicant’s scope/specification for these soil investigations, they have not been asked to take responsibility for or comment on the number/position of the boreholes.

Has the applicant given geodetic positions for these boreholes? Or have they simply marked a site plan giving approximate locations? The significance of this is that without independent observation the IWC cannot confirm with any degree of confidence where the borehole samples were actually taken from.

Important to verify data
The importance of being able to verify soils data cannot be overstated, especially bearing in mind that the applicant claimed that no asbestos was found on site from a previous soils investigation.

However they failed to mention that unless the laboratory is specifically instructed to test for asbestos then none will be found. Moreover 60% of the samples collected could not receive accreditation because either incorrect procedures had been used or they had suffered interference.

Comprehensive and representative samples needed
Professionals continuously involved with soils investigations are well aware of the potential shortcomings of such surveys and how reports can be influenced. It is therefore extremely important that the information is seen to be gathered in a credible way i.e. with sufficient numbers of boreholes at sufficient depths and intervals in order to obtain a comprehensive and representative sample of ground conditions over the whole site.

In this case the applicant has stated that 9 boreholes will be taken on a 60 metre grid over the site. On first impressions this seems a reasonable approach. However when one looks at the location plan for these boreholes it becomes evident that they are on the widest grid possible with the majority (two thirds) on the periphery of the site where there is likely to be least contamination.

Boreholes need to be correctly sited
To give an analogy, the further one goes from the source of noise, the less sound one hears until a point is reached whereby it is impossible to distinguish the original noise from any background sound.

The same principle applies to contamination. The further one goes from the central location of any ground contamination the less contamination is encountered until a point is reached whereby none will be present.

Site periphery will be less contaminated
The periphery of the site will self-evidently be the least contaminated. Had both the EA and IWC consultants been asked to comment on and take responsibility for the number/location of boreholes they would have no doubt noted this fact and challenged it. If, as can happen, the boreholes are in fact taken even closer to the river the likelihood is that very little if any contamination will be found and the site declared to have little or no contamination and present a minimal threat (if any) to the environment.

Such a conclusion would not carry any credibility given the extent of ship building/construction activity in Cowes circa 1910 -1950’s (note many houses in the area still have asbestos tiles) which makes it inconceivable that asbestos and heavy metals were not dumped on this site. Note this site received uncontrolled waste deposits since 1913.

Accurate samples needed
To conclude, I would not be surprised, unless the boreholes are taken on a much tighter grid giving a comprehensive and representative sample of ground conditions over the whole site, if, on the present basis, the site were to be declared to have little or insignificant levels of contamination.

I have urged the LPA Case Officer to bear this in mind when considering the results of the investigation and preparing his report.

Image: Jeremy Buckingham MLC under CC BY 2.0

Advertisement
Subscribe
Email updates?
20 Comments
oldest
newest most voted
Inline Feedbacks
View all comments
JamesP
14, January 2013 11:18 am

If 60% of the samples were unusable, at least that many need to be re-taken, surely, if only to fulfil the original brief? And if none of the samples (good or bad) was tested for asbestos, then the results are incomplete and inconclusive. As with children’s homework, it all needs to be done again, and properly this time!

Absence of evidence is not evidence of absence…

James Luke
16, January 2013 11:39 am

The whole system seems to rely on trust with no independent oversight. A major multi-national that will make many millions of pounds in profit should this planning application go ahead. They are paying Consultants to prove that the development should go ahead. I believe this type of analysis should be conducted independently. To make matters worse, it is unclear what the punishment is if the planning application… Read more »

JILL RUSSELL
18, January 2013 1:10 pm

Historical research shows that the perimeter of the site where most of these boreholes will be taken follows the line of enclosure of the former oyster beds and before them the salterns. So whatever soil samples they get from these areas, they won’t provide any worthwhile information about the levels of contamination from the waste which was deposited from at least 1912 onwards (County Press records).

James Luke
6, April 2013 1:58 pm

ASBESTOS CONTAMINATION HAS NOW BEEN CONFIRMED AT THE ASPHALT PLANT SITE. After months or argument and objections concerning the risk of asbestos contamination at the site, the IWC Planning Department has just published the latest soil report. It states, “Asbestos containing materials were encountered within the near surface waste and capping material.” This is after months of denial by the Applicant and accusations of scaremongering by Councillors.… Read more »

wightywight
Reply to  James Luke
6, April 2013 5:14 pm

James Luke: What are the prospects now of the applicant offering to *clean up* the site by removing the ‘top soil’ – not sure how deep the “near surface waste and capping material”..is? Any ideas on that? Is it feasible to clean up a site such as this by digging the contamination out and taking away (to contaminate another site somewhere!!)the soil..? What might be likely costs… Read more »

James Luke
Reply to  wightywight
6, April 2013 10:22 pm

The soil contaminated with Asbestos was going to be excavated and used in the bunds. There are recommendations in the consultants report that any contaminated soil must be capped, all workers should be wearing protective gear, etc. I suspect that if you pay enough it’s possible to clean up most types of contamination. However, this is just one reason to object to this plant. In addition, there… Read more »

tryme
Reply to  James Luke
6, April 2013 10:35 pm

I’m wondering whether cleaning up asbestos outdoors may have implications for more than the protected workers doing the job – fibres floating off in the air, perhaps. Whereas indoors it’s a contained environment.

James Luke
Reply to  tryme
6, April 2013 10:52 pm

Excavating soil contaminated with asbestos immediately adjacent to a public footpath used by runners, cyclists and walkers must be a risk to the public.

tryme
Reply to  James Luke
6, April 2013 5:47 pm

Congratulations James Luke, on getting this far through sheer determination.

James Luke
Reply to  tryme
6, April 2013 5:57 pm

I can’t take any credit for this – the credit goes to Harvey and others who have tirelessly pursued this issue.

Personally, I feel that the Council Officers should have been doing this work!!

My thanks go out to my friends and colleagues in WRAP who have done the real work!

Bystander
Reply to  James Luke
6, April 2013 6:31 pm

@James Luke The treacherous Councillors should hopefully just have time for their swan-song of now accusing the Planning Department of scaremongering before they are unceremoniously dumped in the forthcoming elections.

retiredhack
Reply to  James Luke
6, April 2013 6:33 pm

@James Luke: James (or anyone), can you point me in the direction of (documented) claims by councillors of scaremongering? (I don’t doubt you for a moment that it’s occurred, it’s just that now would be a good time to remind them of what they said.)

James Luke
Reply to  retiredhack
6, April 2013 8:00 pm

Here’s an IWRadio article on the subject =>
http://www.iwradio.co.uk/articles/2012-10-01-anti-asphalt-plant-campaigners-scaremongering

Here’s the OnTheWight article on the subject =>
http://onthewight.com/2012/10/23/david-pughs-anti-asphalt-plant-scaremongering-claim-challenged/

Councillor Pugh highlights a photo image posted on the WRAP web site as an example of scaremongering but then generalises his comment referring to “aspects like that”.

Black Dog
6, April 2013 4:05 pm

James Luke, I take my hat off to you and others for pursuing this matter. The Applicant, The HSE, The Planning Department, Councillors Pugh and Brown – Not fit for purpose This entire application stinks of corruption and must be halted. In fact if the Applicant took the honorable way out and abandoned the PFI contract it would do the Island a big favour. Let us face… Read more »

tryme
6, April 2013 11:17 pm

Re-reading the details at the top of the topic again, about borehole readings, it is breathtaking the applicant thought they could get away with what they supplied. Dozey old Isle of Wight, they’ll never notice… They weren’t reckoning on James Luke et al!

James Luke
Reply to  tryme
6, April 2013 11:30 pm

Harvey and others are the ones to congratulate! Surprisingly, I believe that WRAP’s assessment was that the latest boreholes were still not adequate for a proper assessment. We did not believe that either the number of the position of the boreholes was sufficient to properly evaluate the site …. yet they still turned up contamination. Similar objections are being raised on the air quality assessment. WRAP are… Read more »

tryme
Reply to  James Luke
7, April 2013 12:13 am

Yes, it’s extraordinary that WRAP have had to become experts on this because IWC aren’t doing the job themselves. I can only speculate to myself why this would be so…

Black Dog
Reply to  tryme
7, April 2013 9:47 am

If regime change is is delivered on May 2nd this entire mess will be dealt with swiftly.

By voting in candidates who actually care and represent their wards before party politics, we can take back control from these despots, over inflated directors and officers.

Make your votes count by voting anything other than Conservative

downwind resident
Reply to  James Luke
7, April 2013 1:02 pm

Would that be the same Council Officer who instructed the Regulatory Committee, to ignore the fact that the proposed asphalt plant will be emitting hazardous particulate contamination, at the hearing for the Environmental Permitby Eurovia recently?
Has the statutory ambient air quality survey of the Medina Valley been undertaken yet and if so by whom?
Certainly not the Council officers!

Black Dog
Reply to  downwind resident
7, April 2013 1:31 pm

There are very many unanswered questions regarding this and other contracts this regime has signed the Island up for. If the Independents can prove (with the help of ordinary council workers) wrong-doings, I am absolutely certain that they will pursue any and all legal remedies available to them – No one should be excluded Councillors, Directors (past and present) managers and the companies themselves. So if it… Read more »

reCaptcha Error: grecaptcha is not defined