Undercliff Drive

Undercliff Drive: Work to reinstate access hampered by series of delays (photos)

Since the middle of September, work has been taking place to reinstate vehicle access to the landlocked properties in Undercliff Drive – following the landslide in February 2014.

The work by Island Roads, originally scheduled to be completed in eight weeks, is now in its tenth week, with the original planning application being added to as the work is carried out (ten additional documents added to the planning application since it was approved in August).

Residents: “To me it’s being handled like a DIY job”
The owner of one property in the landlocked area has been providing OnTheWight with regular updates on the work taking place and frankly, it’s been eye opening.

If there had been just one or two mishaps, there’d be nothing to report. But this is different. We’re hearing week after week of work being carried out by contractors that has to be redone.

The property owner says he thinks the project, “is being handled like a DIY job”.

Alleged problems
Here’s a very brief list of some of the problems residents allege have happened. We’re putting these to Island Roads:

  • Path posts placed and removed more than four times
  • 20m of posts put on top of water main
  • Water main had a post driven through it
  • The eastern chicane too narrow and redone twice
  • Posts too short (western end) so extra glued on top with filler around them
  • Kerb stones, etc buried in SSSI area at the rear of Woodington
  • New road built on mud
  • Fence post by Woodlands – placed in plastic tube attached to wire cage of gabion so when soil compacted, the wires move and so the fence posts move too – gabions removed and replaced
  • 60 tonnes of dry earth dumped at eastern end above the concrete bar
  • When earth delivered it was put on the new road and damaged the road
  • IR hadn’t engaged utility services early enough – water/electricity – workman tarmacked over road before cables buried
  • At the eastern end the drain is higher than rest of road so water can’t drain off

The work so far
OnTheWight popped down to see the progress of the works at the beginning of the month and were initially impressed with how it was looking.

Revisiting last Friday, it was disappointing to see the project has taken another step backwards.

These series of photos below show work completed by 7 November 2016, 19 November 2016 and one going back to Feb 2014.

The Eastern end and turning head
Click on images to see larger versions, description and date taken
Undercliff Drive - the Eastern End (7th November 2016)
Undercliff Drive - the Eastern turning head (7th November 2016)

Footpath chicane and bollard installed and then moved
Click on images to see larger versions, description and date taken
Undercliff Drive - the Eastern End footpath (7th November 2016)
Undercliff Drive - a week later the chicane has moved (19th November 2016)
Undercliff Drive - Chicane moved and extended (19th November 2016)

The concrete bar was installed during works Oct 2013
Click on images to see larger versions, description and date taken
Undercliff Drive - the Eastern End (7th November 2016)
Undercliff Drive - the Eastern End (7th November 2016)
Undercliff Drive - the concrete bar has moved down the slope because it is not attached to anything (7th November 2016)
Undercliff Drive - see how the concrete bar has broken (7th November 2016)
This is the concrete bar in Feb 2014 - note how much higher the other end is

Fence posts installed into moving gabions
Click on images to see larger versions, description and date taken
Undercliff Drive - the posts in the gabions are already leaning (7th November 2016)
Undercliff Drive - the posts in the gabions are already leaning (7th November 2016)
Undercliff Drive - a week later footpath being rebuilt due to moving fence posts (19th November 2016)
Undercliff Drive - Gabions removed as fence posts installed into them moving (19th November 2016)
Undercliff Drive - open site (19th November 2016)

A sad reminder
Click on images to see larger versions, description and date taken
Undercliff Drive - a sad reminder for residents of what was supposed to be (7th November 2016)

The Western end of the landlocked area – where road was built, then moved, then extended, white lines painted on, then removed, painted on again
Click on images to see larger versions, description and date taken
Undercliff Drive - the Western end (7th November 2016)
Undercliff drive - Western end after rain (19th November 2016)
Undercliff Drive - the Western end (7th November 2016)
Undercliff Drive - the Western end (7th November 2016)
Undercliff Drive - Western end extended again (19th November 2016)
Undercliff Drive - One of the extended sections (19th November 2016)
Undercliff Drive - the Western end (7th November 2016)
Undercliff Drive - the Western end turning head (7th November 2016)

Seeking response from Island Roads
It seems to be one thing after another for the residents of Undercliff Drive (and that includes the ones on the outside of the landlocked area too).

OnTheWight has written to Island Roads about the situation, but experience has taught not to wait for an answer before publishing.

The last media query we placed with them about Undercliff Drive took four weeks to get a response. Sadly the response they gave didn’t answer the question we’d posed.

Hopefully this time the response will be far quicker. It’s the very least the residents deserve.

Advertisement
Subscribe
Email updates?
23 Comments
oldest
newest most voted
Inline Feedbacks
View all comments