Isle of Wight roadworks or road closures starting today or tomorrow.
Information provided by Elgin via Roadworks.org. It covers work carried out by BT, utility companies and Island roads.
Streetworks / Licence, Streetworks
Vehicle Crossing Construction by Steve Cox Builders
Responsibility for works: Island Roads on behalf of the Isle of Wight Council
Footway closure
Name: Cemetery Road, Binstead
Location: at Cemetery Road, Binstead, Isle of Wight (CemeteryRoad, Binstead)
13 October — 14 October
Responsibility: Island Roads on behalf of the Isle of Wight Council
Status: In progress
Fairlee Road, Newport, Isle Of Wight
14 October — 18 October
Delays likely Traffic control (two-way signals)
Works location: Newport: Outside 1 Carson Mews,: Fairlee Road-Newport
Works description: C/W Defect X 1 Loose/Rocking Manhole Cover In A Newly Surfaced Cip Road. Replace The Faulty Cover With New. Tm- 3 Way Ttl Incorporated With The Lights At Seaclose Jct. (Cw: Irnwk Not Exceed +Or- 20mm) Newport
Responsibility for works: Island Roads on behalf of the Isle of Wight Council
Current status: Advanced planning
Green Lane, Shanklin, Isle Of Wight
14 October — 31 October
Delays likely Road closure
Works location: Shanklin: From Landguard Manor Road To Witbank Gardens (Ml430256): Green Lane-Shanklin:; Eric Longworth
Works description: Carriageway Reconstruction, Planing And Resurfacing. (Ff-Stren100:U/H4, F1-Strengthen 30mm Fibrovia And 70mm Foambase-Urban:H4) Shankl
Responsibility for works: Island Roads on behalf of the Isle of Wight Council
Current status: Advanced planning
Green Lane, Shanklin, Isle Of Wight
14 October — 31 October
Delays likely Road closure
Works location: Shanklin: From Wheeler Way 190m Southeast, Ml 430258: Green Lane-Shanklin
Works description: Carriageway Reconstruction, Planing And Resurfacing. (Cc-Recon20%:U/H4 20% Concrete) Reconstruction And Seal Joints – Urban:H4 Shanklin
Responsibility for works: Island Roads on behalf of the Isle of Wight Council
Current status: Advanced planning
Bullys Hill, Brading, Isle Of Wight
13 October — 15 October
Delays possible Traffic control (multi-way signals)
Works location: Brading: S/E C/W, 20m From The Junction Of The Mall, Alongside A Property High Down (As Marked Onsite): Bullys
Works description: Carriageway Ironworks – Post Cip Rd Supply And Install A New Gully Frame And Cover Tm Three Way Lights Req (Gl: Ironwork Rocking/Corrosion) Brading
Responsibility for works: Island Roads on behalf of the Isle of Wight Council
Current status: Advanced planning
Pyle Street, Newport, Isle Of Wight
13 October — 19 October
Delays possible Some carriageway incursion
Works location: In Parking Bays Opposite Bhs
Works description: Skip
Responsibility for works: Island Roads on behalf of the Isle of Wight Council
Current status: Advanced planning
High Street, Cowes, Isle Of Wight
14 October — 27 October
Delays unlikely Some carriageway incursion
Works location: O/S 71
Works description: Scaffold
Responsibility for works: Island Roads on behalf of the Isle of Wight Council
Current status: Advanced planning
High Street, Oakfield, Ryde, Isle Of Wight
14 October — 20 October
Delays unlikely Some carriageway incursion
Works location: O/S 10 High Street, Oakfield,Ryde
Works description: Skip
Responsibility for works: Island Roads on behalf of the Isle of Wight Council
Current status: Advanced planning
Monkton Street, Ryde, Isle Of Wight
13 October — 02 November
Delays unlikely Some carriageway incursion
Works location: O/S 108 Monkton Street,Ryde
Works description: Scaffold
Responsibility for works: Island Roads on behalf of the Isle of Wight Council
Current status: Advanced planning
Mount Pleasant Road, Newport, Isle Of Wight
14 October — 27 October
Delays unlikely Some carriageway incursion
Works location: Opposite 8 Mount Pleasant Road
Works description: Excavation Of Joint Hole In Footway To Install Electrical Supply To New Properties
Responsibility for works: Southern Electric
Current status: Advanced planning