New Cowes Enterprise College building not opening when hoped

More to follow on this shortly, but in the meantime, this in from the council, in their own words. Ed

The new £32 million Cowes Enterprise College building will be open in time for the second half of the autumn term.

Artists impression:It had been hoped the state of the art school would be available for the start of the autumn term, but the sustained period of wet weather has affected works on site and pushed the completion date back by a short period.

Seven week delay
Because the move from the adjacent former building to the new facility needs to be done out of term time, the final transfer of equipment and furniture to the new building will be undertaken during the half-term holiday break at the end of October.

The first day pupils will be taught in the new surroundings will be during the first week after the half-term holiday break. The college will provide information on the final arrangements to all parents by the end of September.

The new school, paid for by government grant, will provide one of the UK’s most modern learning environments featuring facilities including a 650-seat conference centre/auditorium, multi-use games area, a green gym, early year’s provision and outdoor amphitheatre – all for the community to also enjoy when not in school use.

Short delay is not surprising
Rachael Fidler, chair of Cowes Pathfinder Trust, said: “Whilst we are excited about using the college’s new building with its exceptional facilities for business education, performance and community use, this short delay is not surprising given the complexity of the new building and the adverse weather conditions during the spring and early summer.”

Alan Wells, chair of the college governing body said: “We are sure the college staff will manage the delay with no impact upon the education of students and that the time will be effectively used to introduce all to the new building prior to the October handover.”

Allows us to familiarise students and staff with the new building
College principal, Jonathan Russell, said: “Both I and my staff fully support the decision of the college trust and governing body not to rush through handover.

“While we and our students are eager to reap the benefits of what will be one of the country’s most outstanding educational environments, this small delay allows us the opportunity to effectively familiarise our students and staff with the new building prior to our full occupation.”

Transfer must happen out of term time
Janet Newton, Isle of Wight Council deputy director of schools and education services, said: “We are confident the building will actually be ready to handover in September but we have to plan around a school holiday to transfer all the necessary equipment and furniture. It would cause too much disruption to do this in term time

“I am sure that most people, given the bad weather, will appreciate the reasons for this small delay. We have managed to keep on schedule in our other main current school rebuild projects – at Haylands Primary School and St Francis and Ventnor – but the complexities and size of the scheme means there have been some unavoidable delays at Cowes.”

Advertisement
Subscribe
Email updates?
2 Comments
oldest
newest most voted
Inline Feedbacks
View all comments